Chelsea Group “In the LEED” at World Trade Center #7
The Plan:
Obtaining
LEED certification required the joint effort of the team led by
Tishman Construction and a consortium of experts through Chrisner
Group that included Chelsea Group, Ltd. The Chelsea team refined the
draft Construction Indoor Air Quality (IAQ) Management Plan that
Tishman initiated for the new World Trade Center #7, the first
building to be constructed on the site after the September 11, 2001,
tragedy.
The project was registered with the U.S. Green Building Council’s
Leadership in Energy and Environmental Design (LEED) certification
for Core & Shell construction, and represented the contractor’s
first foray into the green building program. Tishman recognized that
Chelsea Group could assist them in developing a plan meeting the
specific requirements for LEED certification.
Chelsea Group Intervention:
In accordance with the LEED criteria, Chelsea Group helped orient
the Construction IAQ Management Plan to meet elements of the Sheet
Metal and Air Conditioning Contractors National Association (SMACNA)
IAQ Guideline for Occupied Buildings under Construction.
HVAC EQUIPMENT PROTECTION
Chelsea
Group detailed the steps to be taken in the delivery, storage, and
protection of HVAC equipment installed in the project. This aspect
of the plan involved such actions as keeping delivered equipment
wrapped and off the floor for protection against water damage.
Filtration requirements and operation of the HVAC system during
construction was addressed as part of this plan.
Immediate results: New HVAC equipment was successfully
protected from the elements and installed in pristine condition.
Chelsea Group’s steps in the protection of the HVAC system
allowed the units to operate effectively as needed during
construction.
PATHWAY INTERRUPTION
Chelsea
Group required that all wet processes be conducted in a manner that
did not impact adjacent spaces already constructed. In this case,
before spray-on fireproofing was applied in one area, plastic
sheeting was installed to segregate that space from the remainder of
the construction area. Environmentally safe products were also
utilized during the construction process. Local exhaust and air
cleaning was also required in appropriate situations.
Immediate results: Areas in which construction was
complete were kept clean and free of contamination from adjacent
ongoing construction.
SOURCE CONTROL
Potential sources for airborne contaminants needed to be
minimized. Chelsea Group specified clean-burning stationary
equipment fueled by ultra-low-sulfur diesel fuel. Construction
spaces having high levels of volatile organic compounds required
local exhaust and air cleaning.
Immediate results: These guidelines minimized
pollutants introduced to the spaces during construction.
HOUSEKEEPING
Chelsea
Group required that all work areas be cleaned at the end of each
shift to minimize dust and debris build-up during the construction
phase of the project. All areas were required to be thoroughly
cleaned prior to closing up inaccessible areas such as wall and
ceiling cavities. Spill control was formalized to assure prompt
clean-up procedures, maintaining a safe and clean work environment.
Immediate results: Housekeeping was a regular, ongoing
task, rather than a significant, difficult-to-accomplish final
step in the process. As a result, future occupants will be
protected from potential contaminants that might have otherwise
been trapped in the completed building.
SCHEDULING
The Construction IAQ Management Plan recommended that material
deliveries take place as the materials were to be used. If this were
not possible, materials were to be stored in dry, clean storage
areas, properly protected against weather conditions. In addition,
temperature and humidity conditions were monitored in all areas
where construction materials were stored to document proper
environmental controls.
Immediate results: Because of carefully scheduled
deliveries and proper storage, loss due to damage of
construction materials was minimized, providing a cost savings
for the contractor.
Final Results:
The
Construction IAQ Management Plan was written into the contractual
obligations of all sub-contractors and was integrated into the
construction process. The result was a cohesive project that ensured
proper IAQ during the entire term of the construction. The joint
effort of Chelsea Group and Tishman produced a plan that enabled the
team to secure the LEED Credit necessary for certification.
|